J-1498 · Three phase upgrade

Ben Achterberg · 71 Salisbury Road, Camperdown
Lost

What the job is

Home — Ausgrid application already lodged.

Priced from the catalogue

CodeDescriptionQtyUnitAmount
SWB-3PH-36Distribution board, three phase, 36 pole1$690.00$690.00
SWB-MTR-1PMeter panel upgrade kit, single phase1$410.00$410.00
RCBO-32RCBO 32A 30mA, double pole3$105.00$315.00
MAIN-SW-63Main switch, 63A double pole1$88.00$88.00
TPS-6TPS twin & earth 6mm, 50m roll1$305.00$305.00
LAB-L2Level 2 authorised service worklabour9$185.00$1,665.00
LAB-SNRSenior electrician / A-gradelabour10$145.00$1,450.00
LAB-APPApprenticelabour8$68.00$544.00
LAB-COMPCompliance certificate and paperworklabour1$55.00$55.00
Subtotal$5,522.00
GST$552.20
Total inc GST$6,074.20
Estimated cost / margin$2,852.00 · 48%

Paperwork

DocumentStatusIssuedDue / valid toTotal
QT-2403 quoteExpired27 Apr 202627 May 2026$6,074.20

Move it along

Allowed next steps only. The lifecycle is enforced, so a job can never be in two states at once.

Detail

Logged
23 Apr 2026 by phone
Quoted
27 Apr 2026
Booked
Completed
Invoiced
Paid
Lead
Rob Kalani
Category
Switchboard
Terms
7 days
Origin
migrated history

What happened

  • 28 Jul 2026 · SW
    Quote expired, no response from customer
  • 27 Apr 2026 · DN
    Quote issued
  • 23 Apr 2026 · SW
    Enquiry received by phone