J-1174 · Three phase upgrade
Botany Cold Storage Pty Ltd · 210 Coward Street, Mascot
PaidHigh
What the job is
Coward St cold store — Ausgrid application already lodged.
Note: ducted aircon plus EV, single phase will not carry it
Priced from the catalogue
| Code | Description | Qty | Unit | Amount | |
|---|---|---|---|---|---|
| SWB-3PH-36 | Distribution board, three phase, 36 pole | 1 | $690.00 | $690.00 | |
| SWB-MTR-1P | Meter panel upgrade kit, single phase | 1 | $410.00 | $410.00 | |
| RCBO-32 | RCBO 32A 30mA, double pole | 3 | $105.00 | $315.00 | |
| MAIN-SW-63 | Main switch, 63A double pole | 1 | $88.00 | $88.00 | |
| TPS-6 | TPS twin & earth 6mm, 50m roll | 2 | $305.00 | $610.00 | |
| LAB-L2 | Level 2 authorised service worklabour | 6 | $185.00 | $1,110.00 | |
| LAB-SNR | Senior electrician / A-gradelabour | 8 | $145.00 | $1,160.00 | |
| LAB-APP | Apprenticelabour | 9 | $68.00 | $612.00 | |
| LAB-COMP | Compliance certificate and paperworklabour | 1 | $55.00 | $55.00 | |
| Subtotal | $5,050.00 | ||||
| GST | $505.00 | ||||
| Total inc GST | $5,555.00 | ||||
| Estimated cost / margin | $2,658.00 · 47% | ||||
Paperwork
Move it along
This job is closed. Nothing further to do.
Allowed next steps only. The lifecycle is enforced, so a job can never be in two states at once.Detail
- Logged
- 28 Jul 2025 by phone
- Quoted
- 29 Jul 2025
- Booked
- 4 Aug 2025
- Completed
- 5 Aug 2025
- Invoiced
- 16 Aug 2025
- Paid
- 30 Aug 2025
- Lead
- Rob Kalani
- Category
- Switchboard
- Terms
- 30 days
- Origin
- migrated history
Who is on it
| MF Mick Farrelly | Mon 4 Aug | 8h |
| MF Mick Farrelly | Tue 5 Aug | 8h |
What happened
- 30 Aug 2025 · PRPayment received
- 16 Aug 2025 · PRInvoice raised
- 5 Aug 2025 · RKWork completed by RK
- 4 Aug 2025 · SWBooked in for 2025-08-04
- 29 Jul 2025 · DNQuote issued
- 28 Jul 2025 · SWEnquiry received by phone