J-1174 · Three phase upgrade

Botany Cold Storage Pty Ltd · 210 Coward Street, Mascot
PaidHigh

What the job is

Coward St cold store — Ausgrid application already lodged.

Note: ducted aircon plus EV, single phase will not carry it

Priced from the catalogue

CodeDescriptionQtyUnitAmount
SWB-3PH-36Distribution board, three phase, 36 pole1$690.00$690.00
SWB-MTR-1PMeter panel upgrade kit, single phase1$410.00$410.00
RCBO-32RCBO 32A 30mA, double pole3$105.00$315.00
MAIN-SW-63Main switch, 63A double pole1$88.00$88.00
TPS-6TPS twin & earth 6mm, 50m roll2$305.00$610.00
LAB-L2Level 2 authorised service worklabour6$185.00$1,110.00
LAB-SNRSenior electrician / A-gradelabour8$145.00$1,160.00
LAB-APPApprenticelabour9$68.00$612.00
LAB-COMPCompliance certificate and paperworklabour1$55.00$55.00
Subtotal$5,050.00
GST$505.00
Total inc GST$5,555.00
Estimated cost / margin$2,658.00 · 47%

Paperwork

DocumentStatusIssuedDue / valid toTotal
QT-2136 quoteAccepted29 Jul 202528 Aug 2025$5,555.00
INV-4106 invoicePaid16 Aug 202515 Sep 2025$5,555.00

Move it along

This job is closed. Nothing further to do.
Allowed next steps only. The lifecycle is enforced, so a job can never be in two states at once.

Detail

Logged
28 Jul 2025 by phone
Quoted
29 Jul 2025
Booked
4 Aug 2025
Completed
5 Aug 2025
Invoiced
16 Aug 2025
Paid
30 Aug 2025
Lead
Rob Kalani
Category
Switchboard
Terms
30 days
Origin
migrated history

Who is on it

MF Mick FarrellyMon 4 Aug8h
MF Mick FarrellyTue 5 Aug8h

What happened

  • 30 Aug 2025 · PR
    Payment received
  • 16 Aug 2025 · PR
    Invoice raised
  • 5 Aug 2025 · RK
    Work completed by RK
  • 4 Aug 2025 · SW
    Booked in for 2025-08-04
  • 29 Jul 2025 · DN
    Quote issued
  • 28 Jul 2025 · SW
    Enquiry received by phone