J-1039 · EV charger installation — three phase

Tempe Trade Supplies · 77 Unwins Bridge Road, St Peters
Lost
Site access: Forklift traffic — hi-vis required

What the job is

Unwins Bridge warehouse — wants OCPP so they can bill drivers.

Priced from the catalogue

CodeDescriptionQtyUnitAmount
EV-22KWEV charger 22kW, three phase2$2,050.00$4,100.00
TPS-6TPS twin & earth 6mm, 50m roll2$305.00$610.00
RCBO-32RCBO 32A 30mA, double pole2$105.00$210.00
EV-CT-CLAMPLoad management CT clamp kit1$175.00$175.00
ORANGE-16Orange circular conduit 16mm, 4m length6$14.50$87.00
LAB-SNRSenior electrician / A-gradelabour11$145.00$1,595.00
LAB-ELECElectricianlabour8$125.00$1,000.00
LAB-COMPCompliance certificate and paperworklabour1$55.00$55.00
Subtotal$7,832.00
GST$783.20
Total inc GST$8,615.20
Estimated cost / margin$4,772.40 · 39%

Paperwork

DocumentStatusIssuedDue / valid toTotal
QT-2036 quoteExpired14 Apr 202514 May 2025$8,615.20

Move it along

Allowed next steps only. The lifecycle is enforced, so a job can never be in two states at once.

Detail

Logged
8 Apr 2025 by website
Quoted
14 Apr 2025
Booked
Completed
Invoiced
Paid
Lead
Dave Nguyen
Category
EV
Terms
30 days
Origin
migrated history

What happened

  • 15 Jul 2025 · SW
    Quote expired, no response from customer
  • 14 Apr 2025 · DN
    Quote issued
  • 8 Apr 2025 · SW
    Enquiry received by website