J-1266 · RCD compliance audit and report

Alexandria Print Works · 31 Bourke Road, Alexandria
Paid

What the job is

Bourke Rd press floor — report to go to the committee before the AGM.

Note: annual audit across all common area boards

Priced from the catalogue

CodeDescriptionQtyUnitAmount
RCBO-20RCBO 20A 30mA, single pole2$65.00$130.00
LAB-ELECElectricianlabour4$125.00$500.00
LAB-COMPCompliance certificate and paperworklabour1$55.00$55.00
LAB-TESTTest and tag, per itemlabour11$4.50$49.50
Subtotal$734.50
GST$73.45
Total inc GST$807.95
Estimated cost / margin$328.10 · 55%

Paperwork

DocumentStatusIssuedDue / valid toTotal
INV-4158 invoicePaid17 Oct 202516 Nov 2025$807.95

Move it along

This job is closed. Nothing further to do.
Allowed next steps only. The lifecycle is enforced, so a job can never be in two states at once.

Detail

Logged
7 Oct 2025 by phone
Quoted
Booked
17 Oct 2025
Completed
17 Oct 2025
Invoiced
17 Oct 2025
Paid
29 Dec 2025
Lead
Tim Dalgleish
Category
Compliance
Terms
30 days
Origin
migrated history

Who is on it

DN Dave NguyenFri 17 Oct5h

What happened

  • 29 Dec 2025 · PR
    Payment received
  • 17 Oct 2025 · PR
    Invoice raised
  • 17 Oct 2025 · TD
    Work completed by TD
  • 17 Oct 2025 · SW
    Booked in for 2025-10-17
  • 7 Oct 2025 · SW
    Enquiry received by phone