J-1262 · Three phase upgrade
Two Chimneys Espresso · 287 Sydenham Road, Marrickville
Paid
Site access: Before 6am or after 3pm only
What the job is
Sydenham Rd shop — ducted aircon plus EV, single phase will not carry it.
Note: Ausgrid application already lodged
Priced from the catalogue
| Code | Description | Qty | Unit | Amount | |
|---|---|---|---|---|---|
| SWB-3PH-36 | Distribution board, three phase, 36 pole | 1 | $690.00 | $690.00 | |
| SWB-MTR-1P | Meter panel upgrade kit, single phase | 1 | $410.00 | $410.00 | |
| RCBO-32 | RCBO 32A 30mA, double pole | 4 | $105.00 | $420.00 | |
| MAIN-SW-63 | Main switch, 63A double pole | 1 | $88.00 | $88.00 | |
| TPS-6 | TPS twin & earth 6mm, 50m roll | 1 | $305.00 | $305.00 | |
| LAB-L2 | Level 2 authorised service worklabour | 6 | $185.00 | $1,110.00 | |
| LAB-SNR | Senior electrician / A-gradelabour | 8 | $145.00 | $1,160.00 | |
| LAB-APP | Apprenticelabour | 9 | $68.00 | $612.00 | |
| LAB-COMP | Compliance certificate and paperworklabour | 1 | $55.00 | $55.00 | |
| Subtotal | $4,850.00 | ||||
| GST | $485.00 | ||||
| Total inc GST | $5,335.00 | ||||
| Estimated cost / margin | $2,530.00 · 48% | ||||
Paperwork
Move it along
This job is closed. Nothing further to do.
Allowed next steps only. The lifecycle is enforced, so a job can never be in two states at once.Detail
- Logged
- 3 Oct 2025 by phone
- Quoted
- 6 Oct 2025
- Booked
- 10 Nov 2025
- Completed
- 10 Nov 2025
- Invoiced
- 15 Mar 2026
- Paid
- 30 Mar 2026
- Lead
- Rob Kalani
- Category
- Switchboard
- Terms
- 7 days
- Origin
- migrated history
Who is on it
| AP Ana Petrovic | Mon 10 Nov | 9h |
| MF Mick Farrelly | Mon 10 Nov | 9h |
| RK Rob Kalani | Mon 10 Nov | 4.5h |
What happened
- 15 Mar 2026 · PRInvoice raised late — found during a spreadsheet clean up
- 10 Nov 2025 · RKWork completed by RK
- 10 Nov 2025 · SWBooked in for 2025-11-10
- 6 Oct 2025 · DNQuote issued
- 3 Oct 2025 · SWEnquiry received by phone