J-1148 · Three phase upgrade

Helen Vasquez · 19 Tennent Parade, Hurlstone Park
Paid

What the job is

Home — Ausgrid application already lodged.

Note: ducted aircon plus EV, single phase will not carry it

Priced from the catalogue

CodeDescriptionQtyUnitAmount
SWB-3PH-36Distribution board, three phase, 36 pole1$690.00$690.00
SWB-MTR-1PMeter panel upgrade kit, single phase1$410.00$410.00
RCBO-32RCBO 32A 30mA, double pole2$105.00$210.00
MAIN-SW-63Main switch, 63A double pole1$88.00$88.00
TPS-6TPS twin & earth 6mm, 50m roll1$305.00$305.00
LAB-L2Level 2 authorised service worklabour8$185.00$1,480.00
LAB-SNRSenior electrician / A-gradelabour9$145.00$1,305.00
LAB-APPApprenticelabour10$68.00$680.00
LAB-COMPCompliance certificate and paperworklabour1$55.00$55.00
Subtotal$5,223.00
GST$522.30
Total inc GST$5,745.30
Estimated cost / margin$2,696.00 · 48%

Paperwork

DocumentStatusIssuedDue / valid toTotal
QT-2112 quoteAccepted3 Jul 20252 Aug 2025$5,745.30
INV-4201 invoicePaid6 Dec 202513 Dec 2025$5,745.30

Move it along

This job is closed. Nothing further to do.
Allowed next steps only. The lifecycle is enforced, so a job can never be in two states at once.

Detail

Logged
2 Jul 2025 by phone
Quoted
3 Jul 2025
Booked
4 Aug 2025
Completed
4 Aug 2025
Invoiced
6 Dec 2025
Paid
13 Jan 2026
Lead
Rob Kalani
Category
Switchboard
Terms
7 days
Origin
migrated history

Who is on it

RK Rob KalaniMon 4 Aug9h
DN Dave NguyenMon 4 Aug9h

What happened

  • 6 Dec 2025 · PR
    Invoice raised late — found during a spreadsheet clean up
  • 4 Aug 2025 · RK
    Work completed by RK
  • 4 Aug 2025 · SW
    Booked in for 2025-08-04
  • 3 Jul 2025 · DN
    Quote issued
  • 2 Jul 2025 · SW
    Enquiry received by phone